PREVENT MUSINA ELECTRICITY CUTS

IMPACT OF THIS CASE

Eskom gave notice on 29 June 2018 that they would cut off power supply to Musina, due to the fact that the municipality is in breach of settling escalating debt to Eskom. Sakeliga has brought an urgent court application to prevent Eskom from proceeding with its decision. In response, Eskom withdrew their decisions to cut off the electricity supply to Musina.

This victory played an important role in preventing Eskom from holding paying end users hostage to force defaulting municipalities to settle their debts. This case also paved the way for Sakeliga’s participation in the Resillient case, in which legal precedent was established that paying end users may not be held hostage so that intergovernmental disputes can be resolved.

CASE DETAILS

Afrisake NPC and One Other v Eskom Holdings SOC Ltd and Others

Status: 
Complete

Case commenced: 29 June 2018

Court: High Court, Pretoria

COURT PAPERS

[posts_table term="mlo-category:reg-2021-13" columns="title, button" button_text="Download"]

MEDIA STATEMENTS ON THIS CASE